the currently drawn architectural project, the flat has been sold without even the formwork plan being prepared yet, mashallah, I have been asked to prepare the reinforced concrete, but I have hesitations, I wish you help, the 1st degree earthquake zone is a two-storey building, the insistence that it will necessarily be hollow, with the immorality of using every inch of the land. a broken geometry, I tried to create the system by myself, but I am not comfortable, especially the situation of the S04 arm, because of the architectural boundaries and the effort to use every bit of it, makes me think a lot, + 0.40 basement, 292 cm floor heights, the level of the entrance hall to the apartment is required to be -0.40. I thought it would be appropriate, BZ2-qem=2.0kg/cm2 bedding=4000t/m3, there is no groundwater. earthquake joint will be left on the right and left sides of the mass, is it appropriate to take the R coefficient as lower as 4, my experienced brothers and sisters understand the reason, when looking at the project, warn me if I'm wrong please, is the system I installed is healthy, s04 arm is very hard I think it's the age of the day. Is there a healthier way (or size) to connect these two main beams from different angles instead of doing this with the s04 column (or size) without changing the bad architecture, it would be healthier to design the k9 beam as 25x50, or is this beam section of 55x32 sufficient, normally +0.40 basement For the elevation, I usually draw the basement curtain in the project correction from the upper level of the foundation to the level of the basement, I write the elevations and reinforcements, I do not include the foundation curtains on the raft in the program, but they gave the entry from the -0.40 level, if I accept this elevation as the basic upper level, I should not make a basement curtain in the part of the entrance hall Would it be appropriate and sufficient for me to completely tighten the columns in the relevant place, or should I define the basement curtains in the program at the relevant elevations and include them in the account, or should I go to the solution with the basement logic for this lower part and I have interesting plaque balconies, I am adding the exe of the project now. Thank you very much for the analysis, although there is no problem in the analysis (I have full-rigid analysis), when I want to have semi-rigid analysis, I get a warning that the analysis cannot be performed, perform geometry control, I do not like to stick to the program and there are situations that I am uncomfortable with, as I mentioned, this is the first time I have encountered such a problem. I would like to benefit from your experience, good work. I need it urgently!!!