Related to Pleated Flooring Accessories

michael_angelo

New Member
Hello, the program throws flat reinforcements of pleated floors by overlapping them on the beam. Can our reinforcements be laid as 12 meters in order to give less wastage in the reinforcement? Is there any problem with this? Is there anything in the regulations regarding this issue? Or, for example, let's say we threw 12 meters and it came in the middle of the floor. Can we overlap the other 12 meters of reinforcement in the middle of the floor?
 
"michael_angelo":bbzsfzi6" said:
Hi, the program normally overlaps the flat reinforcement of pleated slabs on the beam. Can our reinforcements be laid as 12 meters in order to reduce the waste in the reinforcement? Is there any harm in this? Is there anything in the regulation regarding this issue? Or For example, let's say we threw 12 meters and it came in the middle of the floor.Can we put the other 12 meters of reinforcement on it in the middle of the floor?
ICS 91.080.40 TURKISH STANDARD TS 500/February 2000 Page 42 ARTICLE 9.2 - ADDING THE REINFORCEMENT
 
Back
Top