Hello, I usually check the quantities in the projects I do. This project has approximately 1800 m2 of total reinforcement of around 60,000 t. When it hits a square meter, approximately 32-33 kg of reinforcement comes out. This was the case in my previous project. Both of them are concrete class C30. In my previous works, it was usually between 35-40, I know that 35-40 kg is ideal. I wonder if I am making a technical mistake, I added my project, I would be glad if you could help. Thanks