Hello, can I ask you, the elders, to take a look at the dormitory project, which will be my first experience on this scale? Points that I missed or missed? In particular: -Polygon columns -Several column narrowing between floors (3-8 and 13.) and if there are points that attract your attention, could you please specify? Thanks, good work...
You do not have permission to view link Log in or register now.
 
If there is a security warning in the current link (a friend of mine said so), I made a new download. I think you cannot open the file, so you cannot share your views. I am adding the current link. Thank you, good work..
 
Hello. MY SUGGESTIONS: 1- Columns and curtains; If the column and curtain do not go beyond the forehead on the lower floors, there is no problem, 2- Stair load must be entered on the panels, 3- Is there no elevator tower in the building? 4- If there are no wall loads in the attic, remove the wall loads, check all the wall loads, 5- If I were the rib beams, I would make the column width. 7- Make the EK formwork pl da beam straight (1), the beams are centered on the column (2), leave the shaft gaps taking into account the condition of the asmonel, 8- Take the loads of the stairs in the basement floors, 9- Down in the 2nd and 1st basement landing stairwells and fire escape cavities are not left. Take it easy Unver ÖZCAN EK:
 
By examining each item of your suggestions one by one, I noticed a few points that I missed. Thank you for your interest and suggestions Mr.
 