Beamless slab flooring

Reform Group

New Member
Hello, In the attached project, it gives an error of slab thickness, 34 cm slab only saves. For this, I need to place reinforced concrete calculation axles and valid axle distances, but I couldn't find a solution by myself. How should the reinforced concrete calculation axles be and what should be the valid distances? What else do I need to do? I solved a similar project with the elevator bucket in the middle without any problems. I'll be happy if you can help me. Best regards, good work.
 
Hello, In the project you added, the floor thickness is 21 cm. seems sufficient. The working distances of the reinforcement axles are arranged correctly. However, not the working distance, but the calculation span value is effective in thickness control.
You do not have permission to view link Log in or register now.
Good work
 