The Values in the Report and the 3D Section Effects Do Not Match.

Also, I did not get an answer to this question I asked before. Although stirrup and cross tie openings are 3 cm in column application plans, stirrup lengths are determined according to 3.5 cm. For example, 23 cm stirrups in a 30 column should be 24, but how can we fix this?
 
"MrtGrsl":kv6d2etp" said:
The value of 59tf in section effects is seen as 70tf in the report.
Raw effects are given in 3D visualization and design effects are given in the report. That's why you don't see the same.
 
"MrtGrsl":2zfnavw6" said:
Although I couldn't get an answer to this question I asked before.Although the opening of stirrups and crossties in column application plans is 3 cm, the stirrup lengths are determined according to 3.5 cm. For example, 23 cm stirrups in a 30 column How can we fix this when it should be 24?
Hello, The length of the melt and cross tie depends on the concrete cover you have given in the column parameters. If you take the concrete cover 4 for the column, the value will appear 24 cm.
 
"HakanŞahin":fppfgq5f" said:
"MrtGrsl":fppfgq5f" said:
I also did not get an answer to this question I asked before. Although the spacing of stirrups and crossties is 3 cm in the column application plans, the stirrup lengths are determined according to 3.5 cm. For example, 23 cm stirrups in a 30-column, how can we fix this when it should be 24? It depends on the cover. If you take the concrete cover 4 for the column, the value will appear 24 cm.
This time, the clear concrete cover appears 2.5 cm on the letterheads. The concrete cover is 4.5 in the beam parameters, but the drawn stirrup lengths are as it should be, but 1 cm is missing on the columns and curtains.
 
"MrtGrsl":3ezvhgns" said:
"HakanŞahin":3ezvhgns" said:
"MrtGrsl":3ezvhgns" said:
I couldn't get an answer to this question I asked before, but. Although it is 3 cm, the lengths of stirrups are determined according to 3.5 cm. For example, 23 cm stirrups in a 30-column column, how can we fix this when it should be 24?
Hello, The length of the melt and cross tie depends on the concrete cover you have given in the column parameters. the value will appear 24 cm.
This time, the clear concrete cover appears 2.5 cm on the letterheads. The concrete cover is 4.5 in the beam parameters, but the drawn stirrup lengths are as it should be, but 1 cm is missing on the columns and curtains.
TS500/February 2000 : 0.2 .2 - Concrete Cover Concrete cover is the distance between the center of gravity of the longitudinal reinforcement and the outermost concrete fiber 0.2.15 - Net Concrete Cover The net concrete cover is the distance between the outermost outer surface of the reinforcement and the outermost concrete fiber. l=https://web.itu.edu.tr/mdaskiran/wp-content/uploads/2014/09/TS500.pdf]https://web.itu.edu.tr/mdaskiran/wp-con ... /TS500.pdf[/url] If you press the F1 help key while the beam parameter screen is open, you can access the related program help.
 
"sahinsukru":3nvf799j" said:
If you press the F1 help key while the beam parameter screen is open, you can access the related program help.
Thanks for your answer, but what I mean is for 30 cm width while both column and beam have 4.5cm concrete cover. the stirrup of one is drawn as 23 cm and the other as 24 cm.
 
Back
Top