The places of the curtains are misplaced in the continuous foundation reinforcement expansion.

BetonArt Yapı

New Member
Hello, While I was mapping the project, I noticed that the curtains were misplaced in some Continuous basic reinforcement expansions. What could be the cause of the problem. Good work.
 
Re: Drawing Dimension Disorder This situation was caused by the continuous foundations of St56 and St67. We take the situation into our notes. For solution: -Move the wedding points of St56 and St67 beams on curtain P09 as in the picture. -Get continuous foundation drawing by selecting beams St32-33-34. -Restore the joint points of the St56-67 beams with the undo command after retrieving the drawing. Note: The carrier system type is A14 in the Y direction. You should choose A15.
 
Re: Drawing Size Distortion Thank you for your reply. I would also have a question about curtain openings. When I say get a schematic drawing, the horizontal reinforcements of some curtains are either not drawn or they make 2x as front and back reinforcements, pretending to throw 4 pieces. Example P25 and P11, can you look at the basement curtains?
 
Re: Drawing Dimension Disorder Due to the fact that the reinforcement length on one side of the curtains supported on the column is square, they are drawn 1 cm longer than the reinforcement on the other side. Therefore, two different details need to be given. There does not appear to be a problem in this sense. In your project, I take other situations related to curtain drawings in our notes.
 