The pile is not divided on the raft

YAŞAR YILMAZ

New Member
Hello friends; The reason why I chose Pilye+Flat in raft flooring is because the iron quantity is more appropriate. But why the program does not divide the pile reinforcements longer than 12 meters in raft flooring. There is no such problem in flat rebars and if we adjust the overlap lengths myself for rebars longer than 12m, would it be appropriate? Thank you very much,
 
Hi, Tensile stresses may occur in both the lower and upper parts of the raft flooring at different points. For this reason, it would be appropriate to choose the reinforcement type at the top + flat reinforcement at the bottom. Good work
 
Back
Top