The center of mass is created in ridiculous places.

hatice.mert

New Member
You do not have permission to view link Log in or register now.
i_60s_last_(PRE-ANALYSIS_(2).ide7.html in my old regulation modification project d314 I am constantly getting the error of insufficient reinforcement on the floor and I cannot see the nodal points. On some floors, the center of mass is formed in very absurd places. Can you help me urgently?
 
Due to the problems in the formation of floor meshes, floors on all floors were deleted and redefined. The place you define with the large slab gap at the elevator edge is defined with the slab edge command. You control information such as slab load and thickness. The location of the centers of mass and stiffness in the attached project is as it should be. A problem may have occurred due to tiling errors.
 