Stepping beamless raft plates

qwerty

New Member
"In order to define beamless raft slabs whose elevations bend differently from each other in the program, it is necessary to change the level of the mat slab. The borders of the raft slabs at different levels are bounded by the slab edges drawn in common to each other. For example, a single slab edge is defined in the middle of two adjacent rafts, and the elevations of each of the two slabs are adjusted. The program automatically connects two mats with a vertical plate." I follow the definition exactly, but I can't make the connection between two rafts automatically with a vertical plate to the Program. It just shows the unmounted connection. Can you help me?
 
The program does not create the vertical plate on the reinforced concrete drawing sheet. Do I need to provide vertical slabs between 2 foundations with a curtain (non-continuing basement curtain)? Or would it be more appropriate to use the method you suggested for the elevator shafts that tear the raft foundation and continue?
 
"qwerty":18rra4qp" said:
The program does not program the vertical slab on the reinforced concrete drawing sheet. Do I need to provide the vertical slab between the 2 foundations with a curtain (non-continuing basement curtain)? Or it is better to use the method you suggested for the elevator shafts that tear the raft foundation and continue. would it be appropriate?
In stepped rafts, the curved slab's drawings are not given automatically. You can also model the vertical slab between 2 foundations with a curtain. We suggest the answer to the 1st question, one of the frequently asked questions for the elevator shaft. /forum/viewtopic.php?f=5&t=1573[/url]
 
Back