mehmetserhat
New Member
I have some shortcomings in the attached project, I would be very grateful if you could help. 1 - In some beams on the mezzanine floor, the reinforcements are placed in such a way that they exceed the minimum reinforcement spacing, when I change the diameter of the reinforcement, the situation is not much different. I wonder if I have a chance to automatically place double rows in the program, if not, how should I edit the drawing? 2 - In the basement and on the ground floor, I need to tighten the stirrups on the columns on the 5 axis. Even though I placed them with 7 cm intervals, the control did not accept it. 3 - Since the building has B1 irregularity, the program automatically chose a coefficient smaller than the R coefficient I entered. In this case, should I change the coefficient or should I not interfere with the coefficient? I need urgent help on the issues I wrote above, if you could help me I would be very grateful. Thank you in advance.