Stapling control does not appear in the report in version 10.20

profesyonel

New Member
Although it is selected from the optional report section, I cannot see the raft basic stapling controls when I receive a report. I'm asking for information about the cause.
 
"professional":1m5e3jc5" said:
I cannot see the raft basic stapling controls when I receive a report even though it is selected from the optional report section. I would like information about the reason.
Hello, In the project you added, a plinth curtain is attached to all columns and structural system bulkheads. Stapling control is not performed on columns and carrier curtains connected to basement or basement curtains Note: It would be appropriate to model all curtains as shells in your project.
 
"Levent Özpak":1mryri9l" said:
In the project you added, a plinth curtain is attached to all columns and structural system curtains. Stapling control is not performed on columns and carrier curtains connected to basement or basement curtain walls. Shouldn't it be done or not? Can we check it with explanation like this?
 
Hello there; There is no special article in TBDY regarding the columns connected to the basement walls. Since these elements are connected to the columns and the foundation, they will make a positive contribution to the punching calculation and reduce the out-of-plane shear stresses. If stapling control is desired, analysis can be performed by deleting the sub-basement curtains. In this case, stapling control will be made on the columns. In other conditions, stapling control is not performed here as the element is attached to the column and foundation. Best regards...
 