thank you, but I could not fully understand what you want to express. I wonder if I upload the project, will you have a chance to show it on only one tile?"unver":1wc5ae26" said:Hi There are ribs in the formwork plan. The problem is in the ribs. I think it would be better to put them as console+continuous floors, taking into account the direction of the ribs; the floors adjacent to the outer console floors. The mounting bars to be placed are also placed perpendicular to the rib. Unver ÖZCAN
project attached"unver":2r7adpd5" said:
Thank you I will consider your suggestions."unver":3g5lmqjo" said:Hi. The project is attached. You can also put a circular beam in front of the consoles, Or when you get a drawing on the formwork plan, you can put a constructive beam equal to the thickness of the ribs, The slab live loads can be reduced, and the wall loads can be removed. Ünver ÖZCAN