Three sample project solutions regarding cast-in-situ reinforced concrete structures were made in the training manual published by the Chamber of Engineers and the scientific committee included Nuray Aydınoğlu, Zekai Celep, Erkan Özer and Kutay Özaydın. In the first example, the solution of the building carrier system with high ductility level is made. In the building with BYS=5, A14 and A15 were selected from the table 4.1 and only the regulation article 4.3.4.5 was checked. In the second example, the ductility level mixed sheared/framed building carrier system has been solved. In the building with BYS=4, A21 and A22 were selected from the table 4.1 and only the regulation article 4.3.4.6. control has been made. In the third example, the solution of the building carrier system with a high ductility level curtain / non-beam slab is made. In the building with BYS=3, A13 was selected from the table 4.1 and only the regulation article 4.3.2.4. control has been made.
 