Raft additional reinforcement item number

Berkay

New Member
Greetings; In the projects I solved with İdecad static, I define the pose number while drawing the basic application plan for the additional reinforcements on the raft foundation. While the pose number given to me in the reinforced concrete drawing is number 15, in the static report the additional reinforcements are separated by axis and each axis starts from pose number 1 separately and the drawing and the pose number in the report do not match. The institution to which I have delivered the project wants the poses to match. I would be glad if you help.
 
Hello, Pose numbers are not printed on any element in static reports. The numbers you see in the raft foundation report are the list of reinforcements given in the "Additional Reinforcements" Tab in the raft foundation reinforced concrete dialog. You can compare these two. The pose numbers given in the drawings can only be followed from the quantity report, as it is a situation that concerns the quantity.
 