Dear siromar ; First of all, thank you for your answer. I didn't write this question because I expected everything from the program. I just wanted to write it because I saw it as a shortcoming. In the program TDY 2.5.3.1 control, "the user is forced to enter the appropriate R coefficient by checking whether the shear force is greater than 0.75." says but does not"siromar":10clefto" said:in earthquake zones 3 and 4, normal ductile building is allowed up to toothed cork h>13, plate h>25m regardless of ace, but as you said, your building is 1. Since it is in the earthquake zone, you cannot do a normal ductile solution after it is not as>.75, the program may make such warnings in the future in comparison to the earthquake zone - as - ductility level, but of course we should not expect everything from the program
The program also checks the height of Hn>25m at the same time, but it shouldn't, you will see the warning alphas<0.75 when it doesn't... Thanks, good work"siromar":3ud1yire" said:Hello, Mr. Hakan, there is a trace of normal ductile building in the 3rd and 4th degree earthquake zones, provided that the plaque is Hn<25m and the hollow - cork flooring is Hn<13m. Regardless, for the normal ductile solution, alphas should be > 0.75. Since the building in question has alphas < 0.75, the program should give a warning, good work, greetings
Dear Siromar; This is exactly what I mean. Thank you"siromar":3ndn3rsu" said:Hello, Mr. Hakan, there is a trace of normal ductile building in the 3rd and 4th degree earthquake zones, with the condition of Hn<25m in the slab flooring and Hn<13m in the hollow floor - cork flooring. Regardless, for the normal ductile solution, alphas> 0.75 should be required. Since the aforementioned building has alphas < 0.75, the program should give a warning, good work, greetings