Mr. ideYAPI officials and colleagues: It seems that there is no problem when we get a static report after the analysis in the project we have presented in the appendix. Also, no problems can be found in the geometry check. But; Looking at the reinforced concrete of the beams, it is seen that there is an ab error in the beams. Again the errors disappear when we want to see the "negative" beams with the filter. We present it to your consideration. Project download link
You do not have permission to view link Log in or register now.
 
Re: "Is there a problem or not?" DID NOT UNDERSTAND OS: Microsoft Vista Ultimate x32 Static ver. : ideSTATİK 7.022 x32 Attached file type: Compressed ideSTATİK 7 project.
 
Re: "Is there a problem or not?" DID NOT UNDERSTAND ab error in beams is insufficient clamping length. This error is a warning. It does not give an error when the report is received. good work
 
Re: "Is there a problem or not?" WE DID NOT UNDERSTAND
"canlarins":3b9onmya" said:
Mr. ideYAPI officials and my colleagues: It seems that there is no problem when we get a static report after the analysis in the project we have presented. Also, there is no problem in the geometry control. It seems that there is an ab error. When we want to see the "negative" beams with the filter, the errors disappear again. We submit it to your evaluation. Project download link
You do not have permission to view link Log in or register now.
Hello , ab control is a control added to the program based on TDY 2007 item 3.4.3.1. It is only performed in the reinforced concrete dialog. No warning is given in the reports. Also, whether this control will be carried out can be determined from the Reinforced Concrete/Parameters/Beam Parameters dialog. Good work
 