Dear friends, I have uploaded my first project in the attachment. I would be very grateful if anyone could comment on my mistakes. There are also a few points that bother me. For example, max. Although the reinforcement spacing is 20 cm, there are slabs with reinforcements at 40 cm intervals. I couldn't make sense of the additional reinforcements on the raft basis. I'm waiting for your help..
 
Hello, I did not see a problem with data entry in your project. *Maximum reinforcement spacing in slab parameters refers to the distance between two reinforcements. In the slab reinforced concrete dialog, for example, the reinforcement interval written in the pile column is the distance between the pillars. *There does not appear to be a problem with additional reinforcements on the raft basis. The main reinforcement set as fi18/20 did not meet the bending moments in the entire raft foundation. Additional reinforcement has been added to accommodate these bending moments. Good work
 