More than 12m reinforcement length problem

reddick

New Member
In a project I made in ide 5.511, some iron lengths are more than 12m in foundation and floor beam expansions in the drawings. What can I do? -Combine lengths shorter than 12m are checked in the settings (the drawing did not change even if I tried 11m or removed that option) -The drawing did not change even if I interfered with the breaking points of the length irons in the beam reinforced concrete
 
The program cannot make additions only in reinforcements that do not meet the 12 meter requirement in a single span. In systems with more than one continuity, 12 meters control is done automatically. Although the span of the beam is less than 12 meters, sometimes the total length of the pillars etc. can be more than 12 meters. If this is valid for pillar reinforcement, you can design the beam without pile if it meets the requirements for assembly and flat reinforcement. If it doesn't, you should make manual corrections according to where you want to cut the reinforcement.
 
I called and asked Mr. Levent and said that the program does not do this. But basically it does this splitting thing, but it doesn't do it on the beam.
 
Back
Top