Hello friends; In a project that the building inspection examined, a deficiency was found in the report as if the stapling controls of the curtains were not made. Can you help?
Hello, Panel stapling control is not done automatically. It is among our request notes. You can control according to the information given in Ts 500 item 8.3.1, figure 8.2 and figure 8.4. Good work