In the scaffolding project, I am constantly getting the section insufficient errors. I applied the statements in the opened headers but the problem is not solved. What can I do.
 
Hello, In the project, the scaffolding slab loads were entered too high (eg: 75 tf/m2). After arranging these loads in accordance with the load class of the scaffold (TS EN 12811-4), analyze and check your project.
 