KIRIS CURTAIN COMBINATION

kasky

New Member
There is a problem with the cross curtain composition on 1 FLOOR and the upper floors, although it is completely combined in the mold plan, as it is seen in the picture, the end is empty and the curtain detail drawing is drawn to the cross section, and the rest is not taken into account, how can I find it straight? thanks
You do not have permission to view link Log in or register now.
You do not have permission to view link Log in or register now.
 
According to your calculation, 1 floor bapo6 drawing is correct 1 snow k16 beam drawing is correct If these are the beams and curtains you say, you can check their status from the appendices. THE DRAWINGS AND REINFORCEMENTS ARE PERFECT Take it easy
 
"kasky":2c2qkcb8" said:
k16 and bap06 1st floor
I think you meant the connection of the K14 beam to P06. After arranging the P06 curtain as in the example project on the 1st floor, you should set the K16 beam 20 cm apart from the joint point of the P05-P06 curtain. Define as. Good work
 
When bap06 is brought to the same haza as bap04 and the drawing is taken (240/25), a drawing is formed as in the picture. bap06 is done the same on all floors
You do not have permission to view link Log in or register now.
 
When
"kasky":2dhy4yi0" said:
bap06 is brought to the same haza as bap04 and the drawing is taken (240/25), the drawing is formed as in the picture. bap06 is the same on all floors
1 See my message above.
 