Intensive additional reinforcement in the area where the elevator curtains are located

xavi40

New Member
Good evening. This is how the design was formed in the project I have attached. In the area where the elevator curtains on the raft floor are located, additional reinforcement is intensely formed. How can I optimize this. What should be the choice of reinforcement. Also, how would it be appropriate to model the 45/25 long curtains at the end of the elevator curtains (Is it more correct to enter as a column). What are the mistakes or suggestions in the project? Thank you for your attention in advance Download Link:
You do not have permission to view link Log in or register now.
 
Re: Please Help Hello My Suggestions: --Remove DS's, --There may be 45/45 columns instead of the curtains at the beginning of the elevator curtains, --There are B errors in the columns, - -The narrow sides of the column should not be less than 30 cm, (Some of the B errors are corrected.) - All of the raft reinforcements can be 16, -Take the stiffness of the basement as -1,-2, -Take 0.15 t/m2 without the roof live loads, -Ribs Make the floor thickness 7 cm, -Make the floor 10 cm on the 1st floor, 12 cm on the floor, control the live load, --Increase the elevator load on the elevator machine floor, --Model the ladder and solve it together, --K33-K34 live load more than 0.1, Unver ÖZCAN
 
Back
Top