Dear idecad officials, it is requested that some curtains be canceled in the parts of the basement floor that do not penetrate with the soil, with the renovation project, after the attached project is licensed. Curtains were removed and beams were defined in their place. As a result of the analysis, the basic reinforcement is insufficient. I have added the final version of the project, licensed as idecad, and the basic design as dwg. I would appreciate it if you could help, I should get back to you as soon as possible. (Curtains to be canceled P105-106-107-121) Thank you
 
Re: RADYE TEMEL Hello, when the analysis is performed according to the "Flat connection" method in the Analysis Settings / Foundation Soil tab in your project, the problem of reinforcement insufficiency caused by additional raft reinforcement is resolved.
 