Hollow slab formwork plan (help)

izmirli_35_35

New Member
Where and how would you recommend passing the beams in this project? How about continuity in one direction for any beam? Does it make sense to make a stub to do this as well? Otherwise, how about connecting beams randomly from columns to columns, where the beams will not be visible anyway? I have never solved a completely hollow structure before. Even if I solved it, it was housing projects. The places where the beams would pass were clear. In this project, the beams are always in different directions. Thank you very much if there are friends who can help with this project.
 
The system can be as attached. A better solution can be sought together with the architectural project. With a height of 30 cm, it seems difficult to meet the deflection conditions. In my opinion, do not fall below 35 cm in this project. because with the thought of workplace etc., moving loads can be effective...
 