After the new update, I'm having a short-direction reinforcement problem on the tiles (eaves, consoles, etc.) that we throw around the stairwell. Although there is a calculation axis in the slabs, I cannot see the reinforcement in the calculations and drawings. For example, in the project I took, the 2nd floor D08 slab 1-axis and D09 slab 2-axis reinforcement are not included in the calculations. He'll be glad if you help. Good work.
 
"Erman Güdü":1yuy032w" said:
After the new update, I have a problem with reinforcement in the short direction on the floors (eaves, consoles, etc.) that we put around the stairwell. Although there is a calculation axis on the floors, I cannot see the reinforcement in the calculations and drawings. Floor 1-Axis and D09 Floor 2-Reinforcement in the axis direction is not included in the calculations. It would be appreciated if you could help. Good work.
Hello, For K06 and K09 beams; Beam Settings, "This beam carries the console floor" in the Static/Reinforced Concrete tab. Check the option and have a re-lay analysis.
 
Thank you for your interest. I think the program detects it automatically. As far as I understand, we need to use this type of flooring. Good work.
 
Back
Top