Bored pile system cannot be resolved error

masmay

New Member
GOOD LUCK WITH. I CAN'T ANALYZE THIS SYSTEM WITH BORED PILE. I DID NOT FIND WHERE MY FAULT CAUSED. IT SAYS CHECK WITH GEOMETRIC CONTROLS, BUT THERE IS NO ANNUAL STATUS IN THE LIST OF GEOMETRIC CONTROLS. I WOULD LOVE TO HELP. FILE EXTENSION
You do not have permission to view link Log in or register now.
 
Re: BORED PILE SYSTEM CANNOT BE SOLVE ERROR Hello, in -Analysis Settings/Foundation-Soil Tab, in the pavement interaction-foundation method, give the connection zone enlargement ratio "0.4h" and adjust the height of the soil layers according to the zero elevation. (Add the height below the zero elevation and the foundation height to the height value of the first layer.) The analysis version of the project is attached. Note: It would be appropriate to arrange the variables of the soil layers (adhesion factor, drainage shear resistance, etc.) according to the values given in the soil survey. Good work
 
Levent, I looked at the ground layers. There are 2 layers, which layer is closest to the surface, which one do we enter first?
 
"mkrts88":1308ufmp" said:
levent bey, I looked at the ground layers. There are 2 layers, which layer is closest to the surface, which one we enter first
We enter whichever layer is at the top in the ground report first.
 
Back