Article 3.3.1 of the Earthquake Regulation

ottomancagatay

New Member
0c1d517662f7e47c7b805cfdb4945baf.jpg
For the basement + 4-storey building surrounded by curtains on 4 sides, the Administration asked me to show item B in the report or explain that it provided item B, how do i have to follow a path? I didn't see it in the report. My 2 questions-) Can we make the necessary calculations properly in a system with cork flooring, version 10.03? Are there any issues that we need to pay attention to or that we need to calculate manually? In the DTS 1a school project, we can't build a hollow block, we can do a cork-floored building, right? I wonder if I understood correctly, I would like to get the information of my dear colleagues in the forum. I wish everyone good work. Sent via iPhone using Tapatalk
 
Re: TBDY 3.3.1 1) Make a solution by removing the rigid basement sign you marked in your building. Get a dynamic analysis report for this situation. Then, with the rigid basement marked, analyze and get a dynamic analysis report. Find the ratio from the periods in the two reports. 2) For the beamless floor solution, ideCAD Statik v10.03 does everything "properly" in your words as described in the regulation
 
Re: Earthquake Regulation 3.3.1 article Thank you, Mr. Ismail. I apologize for my expression. I didn't know how to describe it, so I used the word "correct".
 
Re: TBDY 3.3.1
"Ismail Hakki Feeds":25sitbuv" said:
1) Solve by removing the rigid basement sign you marked in your building. Get a dynamic analysis report for this situation. Then analyze when the rigid basement is marked do it and get a dynamic analysis report. Find the ratio from the periods in the two reports. 2) For the beamless tiling solution, ideCAD Static v10.03 does everything "properly" as described in the regulation
hello I have a question while analyzing the project It gives the error "TBDY item 3.3.1.1.B does not provide a rigid basement condition". How can I fix this error?[/b]
 
Re: TBDY 3.3.1
"KLVN":19b32qhh" said:
hello, I have a question too. When analyzing the project, it gives the error "TBDY item 3.3.1.1.B does not provide rigid basement condition" How can I fix this error?[/b]
Hello, analyze the floor that is considered rigid in the floor general settings dialog by unchecking the Rigid-X and Rigid-Y columns.
 