Are these crosses in my performance analysis a problem?

gencideci

New Member
I have shared the single-crossed parts of my performance analysis in the appendix. "Controlled damage" is provided, which is the target performance. but there are places that do not provide on the higher pages. waiting for your valuable comments...
 
Re: These crosses in my performance analysis will be a problem Hello, If the targeted performance level in the build is Controlled Damage, it is not a problem if the Limited Damage performance level control conditions are not met. These red crosses indicate that the Limited damage performance conditions were not met. In TBDY Section 15.5.3.1, the limit situations in which Linear Performance analysis calculation methods can be applied are given. It is said that the linear performance analysis method cannot be applied if one of these items occurs in the building.
 